Below is a brief update on the latest from the oceans development site office:

The rains the week before last meant that a large portion of the last week was dedicated to cleaning up however the contractor are working on the completion of Phase 1 of the Lagoon Dr crossing by the end of this week in preparation for the stormwater calvert diversion. This will result in the road diversion being reversed from Monday next week with completion date targeted for 15 June 2017.

Work underway for the calvert crossing under Lagoon Dr

In addition to this, the contractor has completed the directional drill across Lagoon Dr and down McCausland Crescent and will be constructing a manhole on the southern side of McCausland this week in order to tie in with the stormwater diversion.

Disruptions to Flamingo Lane are drawing to a close and the plan is to close the diversion through the site (linking Ridge Road to Flamingo Lane) in the next 2 weeks.

The opening of the new temporary bus rank off Lighthouse Rd is awaiting final feedback from the City.